If you are planning to start a construction project in Dubai, it's important to obtain the necessary permits and approvals from the appropriate authorities. One of the essential approvals you need to secure is the DDA building permit. This permit is required for any construction or modification of structures for residential, commercial, or industrial purposes in Dubai.
The DDA or Dubai Development Authority is responsible for issuing building permits and ensuring compliance with the necessary regulations and guidelines. The permit requirements may vary depending on the scope and purpose of the project
As an investor or entity, it is crucial to understand the different permits required for your project and comply with the regulations set by the authorities. By obtaining the necessary approvals and permits, you can ensure a smooth construction process and avoid any legal issues in the future.
If you are planning to start a construction project in Dubai and need to obtain DDA building permits, it's best to seek the help of experts in the field. A reliable and experienced consultant can guide you through the permit application process and ensure that your project meets all the necessary requirements. Contact us today to learn more about how we can help you obtain DDA building permits for your construction project in Dubai.
If you are planning a construction project in Dubai, you must be aware of the several types of DDA building permits that are required to be obtained. A land Demarcation Certificate is also mandatory before starting any activity at the site. Let's have a look at the different permits that you need to acquir
This permit is valid for four years and requires an application, appointment letter duly signed by the owner, consultant, and/or contractor, and a fee of AED 1.00 per square foot with a minimum of AED 200.
A Preliminary Design Approval is required before applying for this permit. It is valid for six months and requires an application, appointment letter, and a fee of AED 5,000 or AED 1,000 per Villa.
Another permit that requires a Preliminary Design Approval before applying, the Excavation Permit is valid for six months and requires several documents, including Geotechnical design calculations, Excavation Design Drawings, and No Objection Certificates from relevant authorities. The fee for this permit is AED 5,000 or AED 1,000 per Villa.
Before applying for this permit, you must obtain a Preliminary Design Approval. It is valid for four years and requires several documents, including Geotechnical Design Calculations, Shoring Design Drawings, and No Objection Certificates from relevant authorities. The fee for this permit is AED 0.05 on Total Built-Up-Area per square foot.
Another permit that requires a Preliminary Design Approval, the Piling Permit is valid for four years and requires Geotechnical Design Calculations, Piling Design Drawings, and a Peer Review of the Geotechnical Third-Party Report for building. The fee for this permit is AED 0.1 on Total Built-Up-Area per square foot.
This permit requires a Sub-Structure Design Approval before applying. The fee for this permit is AED 0.2 per square foot on Total Built-Up-Area plus AED 20,000.
It is important to note that an additional fee of AED 10 for Knowledge Dirham and AED 10 for Innovation Dirham is applicable per transaction for all permits. The service process may take up to 5 working days for some permits, while others require only 2 working days. Ensure that you have obtained all the necessary permits before starting your construction project to avoid any legal issues.